DataPro V

Moscow, Ryabinovaya Str. 53 building 5
2023
Launch year
Tier IV
Resiliency level
7 000
Projected capacity
Location
  • Moscow, Ryabinovaya Str. 53 building 5
General information
  • Projected capacity 7 000 racks
  • Projected area 35 000 m²
  • Building ownership
Cooling and refrigeration
  • Cooling redundancy — N+1, each system is independent
  • Modular system of cooling, capacity 125 kWatts.
Power supply
  • General capacity 50 mWatts
  • Two independent electricity inlets
  • IT reservation system — 4/3N
  • UPS Vertiv (Emerson), capacity (2×800) kWatts
  • Cooling system power redundancy — 2N
  • Dynamic UPS capacity 1,520 kWatts each
  • Switchgear, 10 kWatts
  • Dry power transformers with air cooling, 1,600 kWatts each
Security
  • Data center security services operate 24/7/365
  • Buildings and premises fitted with over 450 CCTV cameras with motion detectors
  • CCTV-camera recordings stored for at least 90 days
  • Single monitoring system for all engineering systems indicators
  • Sluice-rooms access to machine rooms
Fire detection
and extinguishing system
  • All areas are equipped with a very early smoke detection apparatus (VESDA)
  • Fully automated fire-alarm system
  • An automatic gaseous fire suppression system is situated below the raised floor and above the false ceiling.
Critical systems management
  • Engineers are available on the premises 24/7/365
  • All systems indicators are gathered into a centralised monitoring system and supervised 24/7/365
More
  • Carrier Neutral Approach
  • 20 operators provide telecommunications services on the premises
  • 3 distribution frames
  • 3 optical inlets
  • Client’s service staff location in close proximity to its equipment
  • Office rental
  • Storage rental
  • Wide range of cloud services
Certificates
  • Uptime Institute Tier IV Design
  • Uptime Institute Tier IV Facility
Close